Getting AroundTop story
NCDOT wants to widen US 64 to six lanes between Apex and Cary, and NCDOT will present its plans Nov. 18
NCDOT now expects US 64 to cost more than $340 million
Sources: The News & Observer, WRAL
View as table
| Value | |
|---|---|
| 2018 estimate (about) | $114 million |
| Now (more than) | $340 million |
If you drive US 64 between Apex and Cary, NCDOT wants your input. The department plans to widen the road from four lanes to six between Salem Street in Apex and US 1 in Cary, with interchanges at Laura Duncan Road and Lake Pine Drive.
The price has grown. NCDOT first expected about $114 million in 2018 and now expects to spend more than $340 million. WRAL says road construction is expected to start in 2031.
- Meeting: Nov. 18, 5 to 8 p.m., John M. Brown Community Center
- Phone: 512-580-8850, project code 2246
- Email: us64-apex-cary@publicinput.com
- Comment deadline: Dec. 17 (N&O) or Dec. 18 (WRAL)
The US 64 project has a long road ahead
- 2018NCDOT first shares its US 64 plans with the public.
- Nov. 18NCDOT holds a public meeting on the plans in Apex.
- Fall 2028Work is scheduled to begin on the CSX railroad bridge over US 64.
- 2031NCDOT expects the bulk of construction to begin.
Sources: The News & Observer, WRAL
Access will change, too. Drivers would no longer reach Costco directly from US 64; they'd use Pine Plaza Drive or a new access road off Laura Duncan. We suggest sending comments early, since the two reports differ by a day on the deadline.